100% candidates have passed the HP2-Z29 exam by the help of CertBus pass guaranteed HP2-Z29 preparation materials. The CertBus HP PDF and VCEs are the latest and cover every knowledge points of HP2-Z29 Delta – Applying HP FlexNetwork Fundamentals certifications. You can try the questions and answerss for an undeniable success in HP2-Z29 exam.

We CertBus has our own expert team. They selected and published the latest HP2-Z29 preparation materials from HP Official Exam-Center: http://www.certgod.com/hp2-z29.html

QUESTION NO:36

A customer needs to upgrade from IBM i 5.4 to 7.1 . The current system is used extensively for Web serving. Extensive database activity is performed in SQL.

Which factor will affect the time to perform the upgrade of the operating system?

A. The ES Type must convert during the IBM i upgrade.

B. The DB2 referential constraints must be manually reestablished.

C. Some database joins must be reformatted to be compliant with new SQL standards.

D. The logical file access paths must be rebuilt into Encoded Vector Indexes (EVI).

Correct Answer: C

QUESTION NO:21

A client has an existing p5 570 that is directly connected to a HMC. The customer will be

purchasing another p5 570. Which of the following solutions would be appropriate to provide

HMC connectivity to the second p5 570?

A. Implement a proxy server to provide multiple sources to one destination

B. Purchase an additional Ethernet adapter for each p5 570 to provide connectivity between the

two

C. Purchase a network hub or switch so both p5 570s can connect to the single HMC

D. Purchase an additional HMC since multiple HMC are required when more than one POWER5

Enterprise class server is used Purchase an additional HMC since multiple HMC? are required

when more than one POWER5 Enterprise class server is used

Answer: C

QUESTION NO: 179

As a result of an acquisition, an administrator is planning to consolidate some single-LPAR POWER6 520

servers onto an existing POWER7 server.

The administrator is attempting to make these 520 systems HMC-managed.

The network connection between the 520 system and an existing operational HMC have been verified and

checked. However the POWER6 machines fail to appear on the HMC panels.

What is the most likely resolution for this issue?

A. The POWER6 boxes need to be reset back to factory defaults.

B. The Flexible Service Processor (FSP) needs to be reset on each POWER6 520.

C. Upgrade to either PowerVM Standard or Enterprise edition.

D. Power cycle the physical system.

Correct Answer: B

QUESTION NO: 58

An Agent is configured to run on many Agent Servers with high threading levels expecting a high

volume of traffic. What happens if the volume of traffic became low?

A. The JMS queues would fill up with too many unprocessed transactions.

B. The system would slow down as there are too many processes running without work to do.

C. The Agent Server would automatically reduce the number of threads based on the number of

transactions.

D. The IBM Sterling Selling and Fulfillment Suite would automatically shutdown redundant agent

server instances.

Answer: B

Explanation:

QUESTION NO:1

A batch job runs daily in the QBATCH subsystem with a run priority of 50. The job normally takes an hour to complete and no other batch jobs run during this time.

The administrator needs to reduce the run time and requests the run priority be lowered to 40. However1 after the change, run time does not decrease.

What is the likely reason that the run time did not decrease?

A. The run priority applies to only interactive jobs.

B. D82 Symmetric Multiprocessing has not been installed.

C. The run priority represents only the relative importance of the job.

D. The system value QPFRADJ (Performance Adjustment) is set to “No adjustment.”

Correct Answer: C