CertBus ensures to provide the most update 70-178 Microsoft Project 2010, Managing Projects exam questions with the most accurate answers. CertBus 70-178 are the most complete and authoritative exam preparation materials with which one can pass the 70-178 exam in an easy way. Preparing for Microsoft 70-178 Microsoft Project 2010, Managing Projects exam is really a tough task to accomplish. But CertBus will simplified the process.

We CertBus has our own expert team. They selected and published the latest 70-178 preparation materials from Microsoft Official Exam-Center: http://www.certgod.com/70-178.html

QUESTION NO:16

One of your tasks in your project plan is 50 percent complete. The task has a finish variance

of 4 days and a work variance of -14 days. Which set of values describes the task?

A. The task is early by 14 days.

B. The task is early by 4 days.

C. The task is late by 4 days.

D. The task is late by 14 days.

Answer: C


QUESTION NO:46

Your project schedule contains both Work and Material resources. The resources are

assigned to tasks and are of either the committed or proposed booking type. You need to

ensure that the project does not contain over-allocated resources. Which feature should you

use?

A. Clear Leveling

B. Assign Resources

C. Resource Pool C Share Resources

D. Level All

Answer: D


QUESTION NO:28

You need to ensure that when you add new tasks, the project schedule doesn’t set a start date

and end date. What should you do?

A. Select Task from the main ribbon menu. Highlight the task that you want to change and

select Manually Schedule.

B. On the Schedule tab of the Project options, change the ‘New tasks created’ option to

Manually Scheduled.

C. On the Advanced tab of the Project options, clear the Automatically add new resources

and tasks check box.

D. On the Display tab of the Project options, clear the Edits to start and finish dates check

box.

E. Click New Tasks and change the option to Auto Scheduled.

Answer: B

Explanation:

When a task is in manually scheduled mode, the Start, Finish, and Duration columns can be

blank.


QUESTION NO:22

All tasks are assigned to multiple team members. A business analyst sends you an e-mail

message that contains the dates of her vacation. You need to modify the schedule to reflect

delays that are caused only by the business analysts vacation dates. What should you do?

A. Modify the start and end dates of all the tasks of the business analyst.

B. Create a new enterprise calendar, and then enter the vacation days.

C. Use the Mark on Track command.

D. Change the working time for the resource calendar of the business analyst.

Answer: D


QUESTION NO:44

You are reviewing the task details of your project. You receive the following warning

message: “This task has resources assigned which are over-allocated.” You need to be able

to identify a possible resolution for the over-allocated resources. What should you do?

A. Change the task type to Fixed Work, and then recalculate the project.

B. Change the task type to Fixed Units, and then recalculate the project.

C. Increase the task duration values for the task.

D. Use the Task Inspector tool.

E. Set the Level Assignments flag to Yes for the task, and then recalculate the schedule.

Answer: D


QUESTION NO:8

You manage a project according to the schedule as shown in the exhibit.

You need to set the Task Mode for task 4 to be the same as task 6. What should you do?

A. Create a task dependency from Task 4 to Task 6.

B. Set Task 4 as critical.

C. Add a 1 day lead to Task 4.

D. Set Task 4 as manually scheduled.

Answer: D

Explanation:

The Gantt bar for task 6 indicates that it is a manually scheduled task.


QUESTION NO:49

Standard working hours are eight hours a day from Monday through Friday. You create a

task of fixed units and set the duration to 2 days. You assign the task to John at 100 percent.

John wants to work only 50 percent on the task. You change Johns assignment units to 50

percent for the task. Which set of values describes the specified task?

A. Duration shows 2 days; Work shows 0 hours

B. Duration shows 4 days; Work shows 16 hours

C. Duration shows 4 days; Work shows 8 hours

D. Duration shows 2 days; Work shows 8 hours

E. Duration shows 2 days; Work shows 16 hours

Answer: B


QUESTION NO:1

A section of your project contains only a summary task along with four subtasks and a

milestone. You discover that the section is located in the incorrect phase and has the

incorrect Work Breakdown Structure (WBS) numbering. You need to move the section to

another phase of the project. You also need to ensure that the section reflects the correct

WBS numbering. What should you do?

A. Select the summary task and change the scheduling mode to Manually Scheduled.

B. Select the entire section and click Move Task.

C. Drag the summary task.

D. Modify the start and finish dates of the summary task.

Answer: C


QUESTION NO:57

You need to replace the resource assignment for an in-progress task. You also need to retain

the Work, Actual Work, Remaining Work, and Baseline data for the task. What should you

do?

A. Use the Resource Name column drop-down list.

B. Use the Resource Pool feature.

C. Use the Team Planner feature.

D. Use the Level Selected feature.

Answer: C

Explanation:


QUESTION NO:45

You track all costs on your project. You need to track task-level airfare costs that do not

depend on the amount of work or duration of a task. What should you do?

A. Use a work type resource.

B. Create a custom field and capture travel costs at the project level.

C. Use a budget resource.

D. Use a cost type resource.

Answer: D

Explanation:

The currency value of cost resources does not depend on the amount of work done on or the

duration of the task that they are assigned to.


CertBus exam braindumps are pass guaranteed. We guarantee your pass for the 70-178 exam successfully with our Microsoft materials. CertBus Microsoft Project 2010, Managing Projects exam PDF and VCE are the latest and most accurate. We have the best Microsoft in our team to make sure CertBus Microsoft Project 2010, Managing Projects exam questions and answers are the most valid. CertBus exam Microsoft Project 2010, Managing Projects exam dumps will help you to be the Microsoft specialist, clear your 70-178 exam and get the final success.

70-178 Latest questions and answers on Google Drive(100% Free Download): https://drive.google.com/file/d/0B_3QX8HGRR1mcUNNamRfUGFKWWM/view?usp=sharing

70-178 Microsoft exam dumps (100% Pass Guaranteed) from CertBus: http://www.certgod.com/70-178.html [100% Exam Pass Guaranteed]

Why select/choose CertBus?

Millions of interested professionals can touch the destination of success in exams by certgod.com. products which would be available, affordable, updated and of really best quality to overcome the difficulties of any course outlines. Questions and Answers material is updated in highly outclass manner on regular basis and material is released periodically and is available in testing centers with whom we are maintaining our relationship to get latest material.

BrandCertbusTestkingPass4sureActualtestsOthers
Price$45.99$124.99$125.99$189$69.99-99.99
Up-to-Date Dumps
Free 365 Days Update
Real Questions
Printable PDF
Test Engine
One Time Purchase
Instant Download
Unlimited Install
100% Pass Guarantee
100% Money Back
Secure Payment
Privacy Protection